Free tools / One feeder between two breakers
Set up your cable once, then check voltage drop, load current and short-circuit current. Switch views below while keeping your inputs in place.
Start with the example, then enter your project values. Results update as you type. These inputs are shared across all three tools. * Required inputs. The fault level is only needed for short-circuit current.
Voltage drop automatically uses 70°C for PVC insulation, its maximum continuous conductor rating. This does not calculate actual heating or ampacity. Short-circuit maximum uses cold 20°C conductors; minimum uses hot 70°C conductors. Both keep the same source, fault type and nominal voltage (c = 1). Single-phase assumes a full-size neutral. For parallel runs, resistance is divided by run count; the entered group reactance is used unchanged. PE conductors are not part of these fault calculations.
Total load current · per phase
35.28A
22.00 kW total electrical input · cos φ 0.9Total voltage drop · origin to cabinet B
0.98%
3.92 V total drop · ≈ 396.08 V at breaker BWithin your 3% total budget
Prospective short-circuit current · breaker B
Add the source fault level
Three-phase symmetrical fault · nominal voltage, c = 1Temperature-based estimates with the same source fault level, X/R and fault type. Network variations and other fault types can give values outside this range; this is not a full design minimum/maximum study.Calculation assumptions
Balanced three-phase AC · lagging power factor · PVC insulation · 70°C automatically for voltage drop · X = 0.08 Ω/km · source X/R = 1. Fault range: hot 70°C minimum / cold 20°C maximum, c = 1.
Print one combined report with all inputs, all three results and the 8space stamp.
The link keeps your inputs after the # in the address, which browsers do not send to a server. Anyone with the link sees the same inputs.
Optional. Saving stores these inputs in your account on our server; nothing is stored unless you save.
Coloured rings = insulation · metal centres = conductors. L = phase · N = neutral · PE = protective earth. Configuration sketch; colours and positions are illustrative, not a termination drawing.
Preliminary estimates for one feeder. Breaker pickup, capacity and thermal comparisons depend on the supplied device data. Cable ampacity, earth faults, required disconnection times, selectivity and full network fault extremes are not established. A qualified designer must verify the complete installation and applicable requirements before equipment selection.
Cable feeder calculation report
0.98%
3.92 V total drop
0.00% upstream + 0.98% feeder
≈ 396.08 V at breaker B
Within the 3% total budget
35.28 A
Total per phase
22.00 kW electrical input
Not calculated
At breaker B
Three-phase symmetrical fault
Temperature-based range · same source
Source fault level not provided.
Current: I = P / (√3 × U × cos φ). Voltage drop: ΔU = √3 × I × (R cos φ + X sin φ), with equivalent per-phase R and X over the one-way length. R uses the PVC maximum continuous rating of 70°C; actual heating is not calculated. Total drop = upstream + feeder, on the same nominal voltage and load basis. Current uses nominal voltage.
5-core cable (3L + N + PE) per run. R = ρL / (S × 1) for identical runs with equal sharing. Entered group X includes mutual coupling and is not divided. Verify grouping, sharing and terminations. PE is excluded from the fault model.
Fault range: hot 70°C (PVC) minimum / cold 20°C maximum. Both use the same source fault level, X/R, fault type and nominal voltage (c = 1). Source/voltage variation and other fault types can fall outside this temperature-based range. Balanced three-phase: source and cable impedances are per phase.
Conventional Cu/Al resistivity; lagging power factor. Method reference: Schneider Electric, Electrical Installation Guide — voltage drop and short-circuit impedance method (electrical-installation.org).
Preliminary calculation · for engineering review
Device comparisons depend on supplied data. Cable ampacity, earth faults, required disconnection times and selectivity are not established. Verify the complete installation before equipment selection. This stamp identifies the calculation tool; it is not an engineering approval.
The method
Convert electrical input power into total feeder current and current per parallel run. Start with kW, supply voltage and power factor, or enter total amps to see the equivalent electrical power.
I = P / (k × U × cos φ)
P is total electrical input power in watts. Use k = 1 and phase–neutral voltage for single-phase, or k = √3 and line–line voltage for balanced three-phase. This gives total current per phase; divide by the number of identical parallel runs for current per run.
A balanced 22 kW electrical load at 400 V and power factor 0.9 draws about 35.28 A per phase. A 4.6 kW single-phase load at 230 V and unity power factor draws 20 A.
Enter the total electrical input power of the load served by this feeder. For balanced three-phase, the calculator distributes that power across the three phases.
Convert mechanical output power to electrical input power first: input kW = output kW / efficiency. For example, 18 kW output at 90% efficiency means 20 kW electrical input. Motor starting current is outside this steady-load calculation.
No. Load current is the current demanded by the connected load. The permitted current-carrying capacity of the cable depends on its construction and installation conditions and is not calculated here.
Know what goes into the result
The cable model uses conventional material resistivity and R = ρL/(S × n), where n is the number of identical parallel runs. At 20°C, ρ is 0.01851 Ω·mm²/m for copper and 0.02941 for aluminium. The 70°C and 90°C values follow the same reference table. Conductor insulation automatically selects 70°C for PVC or 90°C for XLPE for voltage drop. These are maximum continuous conductor ratings, not calculated operating temperatures; verify the cable and termination ratings for the installation. Cable reactance defaults to an example 0.08 Ω/km at 50 Hz and can be changed to match manufacturer data. With parallel runs, enter the equivalent per-phase reactance of the complete group; it is not divided automatically. Closely grouped conductors have mutual coupling.
Voltage drop is a steady-load approximation with lagging power factor. Skin and proximity effects, harmonics, joints, unequal neutrals and unequal parallel runs are not modelled. Every run must have the same material, length, cross-section and conductor layout. Equal current sharing is assumed; the core choice describes the cable and does not establish its current-carrying capacity. Fault current is evaluated with cold 20°C cable resistance for the maximum and hot 70°C (PVC) or 90°C (XLPE) resistance for the minimum. Both use the same fault type, entered source fault level, source X/R and nominal voltage (c = 1). These temperature-based estimates do not cover network or voltage variation, other fault types, a full IEC 60909 study or earth faults.
Enter any known upstream voltage drop to cabinet A on the same nominal voltage basis and under the same load condition. It is added to this feeder’s drop to obtain the total at B. Current remains a nominal-voltage estimate; the upstream network is not recalculated, and the source fault level at A must still be supplied separately.
Method references: Schneider Electric’s Electrical Installation Guide on voltage-drop formulas and short-circuit impedance and conductor resistivity, conductors in parallel, and insulation temperature limits (figure G11). Use verified cable and source data for your project.
Breaker comparisons use generic B/C/D instantaneous pickup bands, or a supplied upper pickup including tolerance. The hot minimum at B is compared with the upper threshold; breaking capacity is compared with the entered source level at A or cold maximum at B. Expert mode overlays both breakers on one time-current graph. Reference B/C/D shapes are illustrative. Optional manufacturer time bands are interpolated only within their supplied range. Neither an overlap nor instantaneous operation identifies a definite winner; full selectivity still requires manufacturer coordination data. The adiabatic thermal check uses I²t ≤ (kS)², with k selected by conductor material and insulation. Enter verified breaker A maximum let-through energy, or a maximum total clearing time of 0.1–5 s over the full relevant fault range. The time method uses full source current in one conductor; neither method takes parallel sharing credit. PE, unequal sharing and internal parallel faults need separate verification.
Connect the rest of your electrical design: layouts, cable routes, schematics and quantities in the 8space workspace.